Questions to answer:
- What is the role of the internal methodologist
- Who should own the forum post
Products should first be evaluated internally before being added to the public roadmap
We should aim for:
- 4 products post DG2 - this ensures EWG does not have conflicting request to build
- 8 products pre DG2 - this is where the operations of launching the product should be sorted out
- 8 products pre DG1 - this is where initial community feedback is provided
- Unlimited products on backlog - this is where the bulk of the research should be completed to understand market opportunity
Process with internal methodologist (not implemented yet)
| Step # |
Step |
Shared |
| 1 |
Determine feasibility of products on backlog |
Internally |
| 2 |
Bring highest opportunity products to roadmap |
Publicly |
| 3 |
Start developing PRD, Commercials and launch plan |
Publicly |
| 4 |
DG |
Publicly |
| 5 |
Launch product |
Publicly |